Budget
Budget
Depending on the billing type the budget will appear slightly different.
Reimbursable: This will display the cost and price for both the budget and actual, along with the remaining balance.
Fixed Price: This will display the Budget, cost and price, while only showing the actual cost, along with the balance.
Scrolling down will show a Graph similar to the one on the dashboard.
Reimbursable will show the Invoiced, WIP and what's Left.
Fixed Price will show the Balance and Actual.
You can select individual work packages to see a more in depth breakdown.
Progress
Progress
The Progress has 4 different units of measure;
Project Progress: Also called Physical or Actual progress. This is the actual work done for each work package as understood and updated by the project manager.
Planned Progress: Is the estimated actual progress for each Work Package. By default this is calculated linear however this can be more controlled with the baseline and forecasting feature. Create an intercom ticket to discuss activating this feature.
Budget Progress: For Reimbursable, the actual revenue / planned revenue. For Fixed Price, the actual cost / planned cost. This is updated on a weekly basis each Friday.
Timeline Progress: Is how far the project is from the start date to end date.
To update Project Progress, select a work package with resources then select the + button next to progress progress
Add the progress percent and date the select confirm.
The line graph will update accordingly
Variation Workflow
Variation Workflow
Navigate to Work Breakdown then select Variation
Select Create Variation then enter the Variation name
Select the WP you want to revise
Click the 3 dots then select Create Revision
This will allow you to make the required revision for the WP
When a revision has been made on a WP you can review the change(s) on the main summary and WP summary
The orange text indicates the impact of the revision
By selecting Variation applied you will also be able to review only the WPs that have been revised
After the revisions have been made you can change the status to indicate it being in review, this will prevent the ability to make further changes to the variation.
Only with draft status can changes be made to the variation
Once the variation has been client approved, only the Project Manager can change to status to Approved
After approved the orange text will change to green to indicate the approved changes