Skip to main content
All CollectionsProteus Feature Flags
Custom view Project Controls
Custom view Project Controls
James Gold avatar
Written by James Gold
Updated over a year ago

Take more granular control over your project with earned value calculations for each Work Package.

Measure your cost per category for each work package and take control of your ITD, VAC, ETC and EAC calculations within every level of your WBS. This feature can work with or without the forecasting functionality. If the Forecasting feature is also turned on, this will then be used for the ETC and EAC calculations.

If you want to customise Proteus your way, contact your Customer Success representative or send us a message. We will then get back to you with further information.

Default State

Deactivated

Did this answer your question?