Baseline and Forecasting

How to set and maintain your Project Baseline and Forecast

James Gold avatar
Written by James Gold
Updated over a week ago

Forecasting

Forecasting is not a default feature you will need to consult customer success to activate this feature.

Open a Project then select Forecasting from the section menu


Baseline

Before you can set the baseline ensure that the start and end date is added for each work package, you will not be able to create your baseline without this.

Select the baseline resource you want to set. It will (by default) open the labour baseline

Allocate a user to the resource by selecting the pen icon

Only users with a discipline and grade assigned can available for selection

Note: the user will still need to be assigned to resources to be able to book their time

Select the hours to be allocated for the user resource (double click the cell)

When assigning hours to weeks you have 2 options, either using the wand you can automatically populate the hours according to the S-Curve selected at the proposal stage.

Or you can manually assign the hours to each week (double click the cell)

Once the hours have been assigned you can select lock baseline

You will not able to make any further changes once it has been locked only a variation with unlock the baseline for that specific work package.

By selecting Review you can view the changes that have been made to the baseline