Procurement

How to create and manage a purchase order from the stage of purchase request to fully receipting

James Gold avatar
Written by James Gold
Updated over a month ago

Creating a Purchase Request

  • Navigate to Purchase request via Project finance

  • Select the 'Create Purchase Request' button in the bottom right corner

  • Select the tick box of the costs to include on the Purchase request

  • Request Details

    • The Purchase Requisitioner can now complete the PR details

    • Select the Budget Holder and Buyer approvers

    • Add the Description, Expected Receipt date and Scope of Work

  • Costs

    • Select the Receipt type for your cost(s) either Quantity or Value based

    • If Value type is selected enter the cost/unit for the cost.

    • If Quantity type is selected enter the quantity for the cost.

    • Select add additional costs if further costs need to be included onto the PR.

  • Suppliers

    • Select the Procurement mode; Single Source, Single Source Justification (SSJ) or Competitive Tender (RFQ)

    • Add the Recommended supplier (No required at this stage if procurement mode is RFQ)

  • Notes

    • Enter any notes that need to be viewed by the Budget holder and/or Buyer

  • If you select the SSJ Procurement mode you will need to complete the SSJ Form, which will create an additional approval flow.

  • Select Create SSJ Form

  • Complete the fields then assign a DOA SSJ Approver

  • Consult a company admin if there are no SSJ approvers to select

  • Once all details have been completed you can submit for approval


Budget Holder PR Approval

  • After the Requisitioner has submitted for approval the Budget holder will be notified via email that they need to review.

  • The Requisitioner can at anytime recall the PR, redrafting and allowing for further changes.

  • Approve will send the PR to final approval/issuing from the Buyer

    • If the PR is SSJ there will be another approval before the Buyer

  • Reject will cancel the PR disallowing any further changes, all costs will be returned to the list to be used for another PR.


SSJ Approval

  • SSJ Approval is only required if SSJ Procurement mode was selected

  • SSJ Approvers are created within the admin console

  • Once the Budget holder has approved the Purchase Request the SSJ DOA assigned to approve the SSJ Form will get an email notification

  • Navigate to SSJ Form to review

  • After reviewing select Reject or Approve

    • Reject will change the procurement mode to RFQ turning into a competitive tender

    • Approve will send the PR to final issuing by the Buyer


Buyer PR Approval/Issuing

  • The buyer will be notified via email that the Purchase request is ready for final approval and/or Issuing

  • Issue is slightly different between Single Source and RFQ

  • For single source select Approve and Raise PO

  • Create and save a note if required

  • For RFQ select Submit for approval

  • Select Approve and Raise PO

  • Create and save a note if required


Managing a Purchase Order

  • Select the PO type (This is selecting the public note) These must first be created in the admin console

  • Select Supplier Currency

  • The conversion rate can be changed manually by an admin user

  • Select Create cost line item(s)

    • Add the description, receipt type, cost, quantity and if required tax %

  • Select the subtract icon to delete a cost line item

  • Select the DOA External Commitment approver

  • Consult a company admin if there are no Approvers to select

  • Select the supplier if RFQ

  • Select the supplier address and delivery address

  • Enter any notes required for subsequent approvers

  • Once all required information has been entered select 'Submit for approval' to gain cost approval from the DOA.


DOA Approval

  • After the Buyer has submitted for approval the DOA Approver(s) will be notified via email that they need to review.

  • The Buyer can at anytime recall the PO, redrafting and allowing for further changes.

  • Approve will send the PO back to the Buyer for Issuing

  • Deny will ask for a 'reason for rejection' which will be added to the notes audit log and the PO will revert back to draft allowing the Buyer to make further changes to resubmit later.


Buyer PO Issuing

  • The buyer will be notified via email that the Purchase Order is ready for Issuing

  • Select 'Issue'


Creating a Receipt

  • All approvers will be notified via email that the PO has progressed from Issued.

  • Select 'Create Receipt' on the PO

  • Add the draft receipt details

    • Invoice Number: The invoice reference for this receipt

    • Approver(s): DOA (approval to pay)

    • Invoice date: The date of invoicing (cannot be a future date)

    • Value/Quantity: The value/quantity for this specific invoice receipt

    • Comments: Any notes required for the approver

  • Select save draft to save the details

    • All fields must be entered to be able to save

  • Select 'Submit for approval' once ready for approval


Receipt Approval

  • Receipt approval is by default Standard, where every approver; Requisitioner, budget holder, buyer and DOA must approve the receipt. However there is also the Simplified option, where you only need the DOA approval.

  • Consult a member of Proteus team to change to simplified.

  • Each Approver will be notified via email when they are required for approval

  • Either select the link on the email or navigate to the PO and receipt on Proteus

  • Review the receipt, add any comments and select Approve or Reject

  • Approval order; Requisitioner, Buyer, Budget Holder and DOA

  • If any of the approvers reject the receipt, it will change to the status rejected. The Creator will be able to edit the receipt and resubmit for approval, going through the approvers for approval once again.