Definition to Active Project
Select ‘Definition’ via the blue menu bar on the left of the screen
Select the Definition to convert to active project record and change status to Approved in the summary section.
Navigating to Projects
Select Projects then select the Project you wish to Manage from the index
Setting the Baseline
Select Baseline
Select either Labour, Expenses or Purchase Costs
Depending on which resources you need to set the baseline for.
Select the Project wand to apply baseline curve
The Baseline Curve is selected for each WP during the Definition creation however it can be changed via the work breakdown within the project.
Select Submit to lock the baseline
Note that if there is a change to the baseline you will need to resubmit the baseline
Procurement
Creating a Purchase Request
Navigate to Finance
Select Create Purchase Request
Enter Purchase Request details
Setting up the VOWD Tracker
Select Finance
Select VOWD Tracking and you can choose the way to view
Enter the Start and End date for each item to be able to apply the VOWD tracker between
Double Click the box and select the yellow calendar icon to change the date
Note you may have to use the slider at the bottom of the screen to view the whole VOWD page
Click the wand Icon to apply VOWD to each Item
You can do this for either the whole project, individual work packages or for each individual item
If you wish to make changes to or update the VOWD Tracker you can lock weeks to make sure they remain unchanged
Click the padlock icon next to the week
Work Package Management
Reviewing Budget Progress
Select Work Breakdown
From within Work Breakdown select ‘Work Package’ and navigate to the Work Package you want to review progress
On the selected Work Package navigate to the ‘Budget’ tab on the right and Review actual progress of the project here
Reviewing Project Progress
Select the ‘Progress’ tab
Select ‘+’ button on the Progress Speedometer,
You can also review the other progress bar for the work package here
Record actual percentage Progress and select date you wish to record this progress on.
Review Supplier budget progress
Select the 'Suppliers’ tab
Review the outstanding VOWD for each PO item
Management of change
Select 'Management of change'
Select Create Variation, enter the name then create
Select the 3 dots of a work package to apply a revision
Once a revision is applied you can now create the variation for that work package
Once the variation is created you can update the status via the status drop down
When the variation has been reviewed an approved the Project manager can apply the variation creating the new baseline
Only the project manager can final approve the variation
Once you have set the new baseline you will also need to go back to the baseline to resubmit the changes (This is shown at the beginning of this article)
Authority For Expenditure
Navigate to Finance
Select AFE
Select create Authority of Expenditure
Enter the details and select create
How to Invoice (if applicable)
Navigate to Finance
Select Invoice
Select Create Invoice
Select PO from the dropdown
Office and Project will be automatically selected when you create an invoice within the project invoicing
Select the add VOWD Costs and other resources to invoice
Select the delivery address then save
Select edit to make further revisions to the invoice
You can either send invoice via Proteus or download the PDF and send externally
Select Send to send via Proteus
Or Download then mark sent once done externally
Once paid select mark paid